INDUSTRY.co.id - Jakarta- The duration of Surabaya-Malang on weekends and long holidays is about 5-6 hours, whereas if the Pandaan-Malang toll has been operated for 1-1.5 hours only.

PT Jasa Marga Tbk's press release details the progress of land acquisition and construction on the five sections of the project as follows:

1. Section I: Pandaan-Purwodadi (14.92 Km), land acquisition progression 85.76 percent, while construction progress 16.10 percent.

2. Section II: Purwodadi-Lawang (8,00 Km), land acquisition progress 79,41 percent, construction progress 3,72 percent.

3. Section III: Lawang-Pakis (7.50 km), land acquisition progression of 95.85 percent, construction progress 2.81 percent.

4. Section IV: Pak I-Pakis II (4.10 Km), land acquisition progression 28.24 percent.

5. Section V: Pakis II-Malang (3.10 Km), land acquisition progression 41,41 percent, construction progress 0,42 percent.
 

The managing director of PT Jasamarga Pandaan Malang, Agus Purnom, said in accordance with the project's Toll Road Concession Agreement (PPJT), the daily traffic (LHR) planned for the Pandaan-Malang toll is 18-20 thousand vehicles per day and the tariff is Rp750 per kilometer.

"Our hope, when operated LHR can approach the peak target," said Agus.

This segment has been highly awaited by the people of Malang and its surroundings because the access road Pandaan-Malang via the national road artery has been very solid.